Jump to content

johnpat

Advanced Stage 3
  • Posts

    390
  • Joined

  • Last visited

Posts posted by johnpat

  1. image.jpeg

     

    you can go from Soi Buakhao to Soi 15 by motorbike now .. not a car yet..

    I'm not sure what's under those mounds of dirt and scrap concrete... something unfinished no doubt.

    image.jpeg

    They have not figured out what to do with the water leak next to the Grand Avenue condo.   They've only been working on it for a month or so, give them time.   You must be patient.

    You an squeeze by on  a motorbike if they're not actively working and accomplishing nothing at this spot.

    cr3.jpg

    On the other end of Soi 15 by Second road it's a complete disaster.  You can see the pipe  with open end buried in the sand

    image.jpeg

    Some good news but hard to see in this picture.   The seem to have finished putting in the concrete surface of Second Road at this point.  The grates are sticking up (eventually they'll put in tarmac as they are doing on Beach Road) but until then you'll not want to drive on this concrete as you'll run into a grate.

     

     

    • Like 5
    • Thanks 1
    • Thumbs Up 1
  2. image.jpeg

    This is the head of the construction work that's been putting wires underground.   They have been moving quickly down second road from the Central Festival Mall and have passed the Royal Garden mall on the way to, one assumes, Pattaya Tai.

    But there's a problem if you turn 180 degrees.

     

    image.jpeg

    There's the soi 15 crew who have been taking forever to make the junction of the soi 15 pipe and the second road pipe.  They've had their side of the road blocked for ages.

     

    If the construction crews meet second road will be shut off completely.

     

    That may explain why the soi 15 crew were working long hours last night but as of this morning there's still a lot of them to do.

     

     

    • Like 1
    • Thanks 1
    • Thumbs Up 2
  3. image.jpeg

    between the Travelodge and the Grand Avenue condo.   Just need to drop a big pipe in there and cover it up..

    image.jpeg

    No progress on the Soi 15 to  Soi Buakhao connection.  

     

     

    image.jpeg

    This is how they fashion grates over the flimsy pipe sticking up.

     

    I drove by the soi 15 and Second Road intersection and it's looking worse than ever.  Two big pits.  Lots of rebar and no sign that they are wrapping up.

     

    • Like 4
  4. 13 hours ago, Yesitisdakid said:

    You bring up a valid point there does not when i looked look like there will be parking in the complex and there will be lots of bikes needing parking

      This is the big mistake Tree Town makes -- they built a nice road  and then didn't use it for what God intended (i.e. motorbike parking) and instead put tables on it.   I like parking close to if not right in front of the place I patronize.  I think most expats have motorbikes and if you want to attract them you need it to be convenient.  

    • Like 2
    • Thumbs Up 2
  5. 4 hours ago, Zeb said:

    Google maps on my mobile phone has a traffic advisory for Soi 15 - showing closed to traffic until end October.

    The 2nd road end of Soi 15 is also shown as closed to traffic for quite a distance - but not down as far as the rear of the Avenue shopping centre etc.

    You can give Google maps feedback as to whether what they are says is accurate as well - for those so inclined.

    End of October has been my guess for a while.  It will make it a nice clean 2 years to complete something that should have taken 2 months.  That's a good measure of incompetence.

    The part Google shows as closed off is way too long which is making it hard to plan trips from City Garden or Urban condos as the first step requires a magic leap to an open road (even though in reality the road is finished in front of those condos).

    Today people had blazed a trail in the dirt road so it was actually possible to drive a car down soi 15 to Second Road.   There's no telling if that will work tomorrow.   It's good that Google be pessimistic if and when they decide to do some serious work on that section again we don't want folks confused and driving into ditches.

     

    • Thumbs Up 3
  6.  

    3 minutes ago, Glasseye said:

     

    What's 2nd Road looking like mate ?   Have they gotten past "The Avenue" or is that area still a massive cluster fcuk ?

     

    The drainage work is mostly done except right near soi 15 where they still have a big open pit with lots of pre-existing pipes visible and I guess they are trying to figure out how to install their big pipe around all the existing plumbing.

     

    However not content to offer the citizens some relief they started two -- count em -- two projects on the left side of Second Road near Central where they are burying electrical cables, making Second Road once again a one lane road and backing up traffic quite a distance (and on Soi Diana too).

     

    • Like 1
  7. aaaa.jpg

    Soi 15 looking up to Soi Buakhao.   Working on laying concrete  but they'll have to drain the lake first.   The pipe on the right is bad news.. looks like that has yet to be put in.  Add another week to the "schedule".

    You can see five visible signs at the Hideaway saying "We are open" with more out of sight to the left.  There's even a signboard outside the entrance proclaiming they are open.

    Are they open?  No they are not.   They will open at 8am.

     

    image.jpeg

    Turning 180 degrees we see that they have actually put down some concrete.    It's only take a few months but we see actual roadway being replaced.  Hooray.

     

    image.jpeg

    A closeup of the place where they must fashion a custom grate over the pipes with the steps leading down.

    In most of the Soi 15 disaster project they dropped big concrete cubes which offered a nice big area that one could enter to clean out the big pipe.  In this project to finish the ends of Soi 15 they've got this new procedure which uses these small pipes as access to big pipe.  Why?  Is it cheaper?  It doesn't seem faster.  It doesn't seem as reliable.

     

     

     

    • Like 3
    • Thanks 1
    • Thumbs Up 2
  8. Soi 15 disaster status:

    Very little work on the Second Road side for  a week or so.    They laid some concrete and built a grate over one of those tubes sticking up and then abandoned the project.

    The photo shows the Soi Buakhao side.   As far as I can tell they've buried the pipe from Soi Buakhao to the Hideaway (and maybe further).   They did not link up the Soi 15 pipe to the Soi Buakhao pipe so that's something that will take a while for them to figure out.  

    The photo shows that they are setting up to lay some concrete on a section of the soi.   Again like on the Second Road side they are not extending the existing concrete on either end but are instead putting some concrete in the middle where it does no one any good.   But it is progress and that is a good thing.

    soi15.jpg

    • Like 4
    • Thanks 1
  9. Cars and motorbikes leaving the Grand Avenue underground garage must do a tight right u-turn into the dirt lot in front of the condo complex, drive through that lot and make a left crossing a dirt bridge to Soi Boomerang.  Then down that Soi and a sharp right past girls sitting outside gentleman's clubs to Soi Buakaow. 

    As a result lots of residents have chosen to park along both sides of the finished part of soi 15 making it a one lane road at places thus sharing their misery with other soi 15 residents.

    So far there has been no visible progress on the link from Soi 15 to Soi Buakaow.    Yes they go out and work with big machines and move dirt around but they've accomplished exactly nothing in these last few months.   Is there anyone in charge?

    grand.jpg

    • Like 1
    • Thumbs Up 4
  10. 13 hours ago, Stillearly said:

     

    following numerous complaints by residents and our own readers at The Pattaya News, Pattaya Mayor Poramase visited the area yesterday and expressed concerns about the lack of lighting and traffic signs.

    He then personally urged the contractor to complete the project by August to return the space for safe public usage.

    Well that's not going to happen.     Maybe it will be done by October but likely November on the two year anniversary of the start of this disaster of a project.   

    I've seen them construct vast roadways such as Highway 7 and now highway 3 south of Pattaya.   Yet just constructing 800 meters of soi 15 takes two years.   It's all about manpower and they did not put enough people and machines on this project from the beginning and continuing to now.  

     

    • Thumbs Up 2
  11. This is where the completed construction of soi 15 will meet with Second road.

    In over a month they've made no discernible progress toward that goal but they have managed to accumulate far more giant pipes than they need to complete this small unfinished section.

    Maybe the construction project is just a ruse and their real work is in buying and selling big pipes.

    20230722_073124.jpg

    20230722_073203.jpg

    20230722_073241.jpg

    • Haha 2
  12. They are rushing to finish second road before the big Marathon this coming weekend.   The biggest problem now is the entrance to soi 15.   

    There are still a lot of imperfections in the new roadway that I know to avoid on my motorbike. I worry the people running down this road before dawn might be twisting their ankle at spots.

     

    • Like 1
    • Thumbs Up 4
  13. This is soi 15 connecting to Second Road.

    They are installing one of those big pipes with a small pipe sticking out.  

    What's that all about?    

    Here's my guess.   What they had been doing for the completed parts of the soi 15 is put in a big concrete block every so many meters and that block would have a drain constructed on top and a big pipe on either end.   So it would serve as a junction point.  

    I have not seen any big concrete blocks for this resumed construction.   Could the small pipe be placed upwards and above it they will construct a drain?  So this pipe section will join two big plastic pipes as well as offering a drain into the big pipes?

    It would be faster than the big concrete block idea but not a sturdy....  I guess we'll see.

    pic.jpg

    • Like 4
    • Great Info 1
  14. 1 hour ago, Derek Dangleberries said:

    Totally characterless!

    To me it just screams out "Let me suck the money out of your wallet in the shortest time possible"

     

    I'm guessing that there will be high tables and chairs along the front adjacent to sidewalk.   After all the main draw of those bars is watching everything go by while enjoying a drink.   Then it will look more cozy at least..

    • Like 2
    • Thumbs Up 3
  15. In November of 2021 they started destroying soi 15 at this end and it looks like they are  finally going to finish the job and connect the soi 15 drainage system with the second road drainage system and restore the roadway completely.

    Then they'll have to work on finishing the other end connecting Soi Buakaow to the Soi 15 drainage system..  

     

    soi15.jpg

    • Like 4
  16. They've begun to move the construction area into the Second Road and Pattaya Tai intersection.

    Looking in the hole I can see problems.  There are a large number of pipes  crossing the trench visible in the hole.  They  drop one of the huge black drainage pipes in the trench like in other places.  They are going to have to relocate all those  small pipes first. 

    const1.jpg

    • Like 4
×
×
  • Create New...